2019 Cost of Wind Energy Review
Summary (5 min read)
Introduction
- Table ES1, Table ES2, Table ES3, Table ES4, and Table ES5 summarize the basic LCOE inputs and outputs for the reference land-based, fixedbottom, and floating offshore wind and residential and commercial distributed wind projects.
- 7 NREL’s 2015 Cost and Scaling Model is used as an internal reference and is not publicly available.
4.3.1 Turbine Parameters
- For the purpose of this report, the turbine parameters are specific to the turbine and independent of the wind resource characteristics.
- These parameters include not only turbine size (such as rated power, rotor diameter, and hub height), but also turbine operating characteristics (such as coefficient of power, maximum tip speed, maximum tip-speed ratio, and drivetrain design).
- Because the three-stage planetary/helical gearbox with a high-speed asynchronous generatorstyle drivetrain topology dominates the U.S. market, the authors selected this type of drivetrain for the baseline wind turbines used in this analysis.
- The power curve for the 2.6-MW land-based wind turbine is derived from NREL’s System Advisor Model.
- For specific approaches regarding additional turbine parameters (e.g., power curves), see the “2010 Cost of Wind Energy Review” (Tegen et al. 2012).
4.3.2 Wind Resource
- The average wind speed varies from project to project across the United States.
- The annual average wind speed chosen for the reference project analysis, which is consistent with prior reports, is 7.25 meters per second (m/s) at 50 meters (m) above ground level (7.89 m/s at a hub height of 90.1 m).
- The representative elevation defines the air density used for calculating the project AEP.
- A summary of the wind resource assumptions for the 2019 representative site is included in Table 6.
- 10 For comparison purposes, last year’s CapEx was inflated from 2018 USD to 2019 USD assuming a 1.8% cumulative rate of inflation from the Bureau of Labor and Statistics .
4.3.3 Losses and Availability
- They are treated as independent of any other input in this simplified analysis.
- Types of losses accounted for here include array wake losses, electric collection and transmission losses (from the substation to the point of interconnection), and blade soiling losses, totaling 15%.
- A wind power plant availability of 98% is assumed, indicating the plant is ready to produce power 98% of the time that the wind speed falls within the operational range (i.e., between the wind turbine’s cut-in and cut-out wind speeds).
- The net average AEP is then calculated by applying all losses and availability to the gross AEP.
- Table 7 shows the estimated losses and availability for the land-based reference wind power plant.
4.3.4 Annual Energy Production
- The AEP for this analysis was computed using the System Advisor Model.
- The result of these calculations yields a net energy capture of 3,734 MWh/MW/year, which corresponds to a 42.6% net capacity factor assuming 8,760 hours in a year.
- O&M market data are not widely available; therefore, the recent U.S. wind industry survey, “Assessing wind power operating costs in the United States: Results from a survey of wind industry experts” (Wiser et al. 2019) is used to inform the O&M cost estimates for the representative wind plant.
- The average across respondents was ~$43/kW/yr and is assumed to be the all-in levelized OpEx for the representative project.
- Financing assumptions, on the other hand, refer to the cost of interest and other carrying charges, corporate taxes, and depreciation (represented by the FCR in this report), applied to the total CapEx.
4.5.1 Discount Rate
- Typically, various financial terms, such as the cost of debt or equity, are captured in the discount rate, which is in turn used to estimate the cost of energy.
- For this analysis, the authors calculate the discount rate as the after-tax weighted-average cost of capital (WACC), and they presume that the reported yields for equity are after-tax yields and can be used directly in the WACC calculation.
- The cost of capital data collected by Lawrence Berkeley National Laboratory (Wiser and Bolinger 2020) gives a basis for WACC assumptions for the representative wind project in 2019 and results in a nominal WACC of 6.32%.
- Because state taxes are normally deductible expenses on federal tax returns, the blended rate is represented as 25.7%, as reported in NREL’s ATB.
- 14 Research has shown that one likely outcome of the termination of the PTC is increased project leverage, which will reduce the higher-cost tax-equity portion of project finance.
4.5.2 Economic Evaluation Metrics
- In the economic evaluation of wind energy investments there are two important metrics: the capital recovery factor (CRF) and FCR.
- Table 10 presents the estimated WACC, CRF, and FCR in nominal and real terms using the after-tax WACC discount rate of 6.32% and 3.72%, respectively, a project design lifetime of 25 years, and a net present value depreciation factor of 84.6% (assuming a 5-year MACRS depreciation schedule).
- For illustrative purposes, the LCOE is calculated for the land-based wind projects installed in 2019 using the same site-specific methodology for 80 project locations, which are shown on the supply curve (marked by green circles).
- The authors assessed a reference project at the fixed-bottom and floating sites, which each comprise 100 wind turbines rated at 6.1 MWsthe turbine capacity estimated from NREL’s global offshore wind project database for calendar year 2019.
- 21 This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
5.3.1 Turbine Parameters
- The offshore wind turbine technology characteristics for this analysis are calculated using a capacity-weighted average of the global offshore wind projects installed in 2018.
- These values and additional assumptions for the offshore turbine characteristics are summarized in Table 15.
5.3.2 Wind Resource
- The authors assessed the wind resource for the fixed-bottom and floating reference sites in the North Atlantic and Pacific Coast, respectively.
- The wind resource parameters are summarized in Table 16.
- 26 This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
5.3.3 Losses and Availability
- The U.S. offshore reference project considers losses from wind power plant array wake impacts, inefficiencies in power collection and transmission, and losses from wind power plant availability.
- These losses and availability estimates are determined using ORCA (Beiter et al. 2016), which performs calculations based on a specific wind power plant layout and site-specific meteorological ocean conditions.
- The total system losses for the fixed-bottom technology in the North Atlantic are 16.0%, whereas the system losses for the floating offshore technology in the Pacific Coast region are 20.9%.
- The primary differences in loss between these offshore technologies are the additional electrical cable losses for floating wind in deeper waters (i.e., 34 m versus 739 m), and wake losses from the different reference sites.
- Table 17 summarizes the losses and availability estimates for the fixed-bottom and floating offshore wind technologies.
5.3.4 Annual Energy Production
- The net AEP is calculated using the wind turbine technology parameters and wind resource inputs, and by applying the appropriate losses and availability estimates.
- The net AEP is calculated for the offshore reference project for both fixed-bottom and floating offshore applications using ORCA.
- 27 This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
- More information on the global trends for offshore wind power plant performance can be found in Musial et al. (2017).
- Vessels, equipment, scheduled maintenance, unscheduled maintenance, land-based support, and administration.
5.5.1 Discount Rate
- An individual project’s financing terms reflect its specific risk profile, assumptions, and ranges of nominal discount rates for offshore wind.
- The generic assumptions used for this report are consistent with NREL’s 2019 ATB (Feldman et al. 2020), which were derived from industry interviews and a literature review.
- For this analysis, the authors assumed the discount rate and other economic evaluation metrics to be similar for the North Atlantic and Pacific Coast representative projects.
- 20 Underlying assumptions for marginal tax rate and inflation are consistent with those presented in Section 4.5.1.
5.5.2 Economic Evaluation Metrics
- To determine the LCOE for the 2019 representative offshore wind projects, a similar FCR methodology that was used for the land-based representative wind project is applied (see Section 4.5) and informed by the 2020 ATB.
- For the offshore wind supply curve, the LCOE for each of the potential wind power plant locations is computed using a site-specific CapEx, OpEx, and net AEP.
- 37 This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
- Table 24 summarizes the costs for the reference projects wind turbine and BOS CapEx components (including their contribution to LCOE).
6.3.1 Turbine Parameters
- For the purpose of this report, the turbine parameters are specific to the turbine and independent of the wind resource characteristics.
- The authors developed the power curve for the 20-kW residential system and the 100-kW commercial system assuming stall-regulated turbines with standard air density.
- The authors used a standard air density of 1.225 kg/m3 for power curve development.
- 38 This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
6.3.2 Wind Resource
- The average wind speed can vary from project to project across the United States.
- This wind speed is intended to be generally indicative of the wind regime for distributed wind projects installed in moderate-quality sites.
- A summary of the wind resource assumptions for the 2019 representative site is included in Table 26.
6.3.3 Losses and Availability
- They are treated as independent of any other input in this simplified analysis.
- Types of losses accounted for here include blade soiling, turbine controls, and grid availability, totaling 11.5%.
- The wind turbine availability is assumed to be 95%, indicating that the wind project is ready to produce power between wind turbine cut-in and cut-out wind speeds 95% of the time.
- Net average AEP is calculated by applying all losses and availability to the gross AEP.
- This report is available at no cost from the National Renewable Energy Laboratory at www.nrel.gov/publications.
6.3.4 Annual Energy Production
- The authors estimated the gross AEP for this analysis using generic power curves for the 20- and 100-kW turbines developed by NREL and computed in Openwind (UL undated).
- The losses and availability are then applied to calculate the net AEP.
- Reference Residential and Commercial Distributed Wind Projects AEP and Capacity Factor Summary AEP and Capacity Factors (6-m/s wind speed at 50 m) Residential (20 kW) Commercial (100 kW) Net energy capture (kWh/kW/yr) 2,580 2,846 Net capacity factor (%) 29.5% 32.5% 6.4 Distributed Wind Operation and Maintenance Expenditures Additional details describing FCR are presented in Section 4.5.
- Financing assumes debt for approximately 60% of the 23 Given the scarcity and varying quality of the data, OpEx may vary substantially among projects, and the data included here may not fully represent the challenges that OpEx present to the distributed wind industry.
6.5.1 Discount Rate
- Typically, various financial terms, such as the cost of debt or equity, are captured in the discount rate, which is in turn used to estimate the cost of energy.
- For this analysis, the discount rate is calculated as the after-tax WACC and it is presumed that the reported yields for equity are aftertax yields and can be used directly in the WACC calculation.
- Each actual project, however, has a unique risk profile, financing terms, and ownership structure.
- For this reason, a single WACC representing the distributed wind installations should be viewed cautiously and used to illustrate general market trends and conditions only.
- This rate aligns with the inflation rate provided in NREL’s ATB.
6.5.2 Economic Evaluation Metrics
- In the economic evaluation of wind energy investments there are two important metrics: the CRF and FCR, with details provided in Section 4.5.2.
- National Renewable Energy Laboratory (NREL), Golden, CO (US).
- A summary of the sensitivity parameters (i.e., capital recovery factor, fixed charge rate, and levelized cost of energy [LCOE]) are shown in Table B2.
- The National Renewable Energy Laboratory’s Offshore Wind Cost Model, also referred to as the Offshore Regional Cost Analyzer, is subject to continuous data updates and validation, which help ensure that the model reflects the latest industry and market developments.
Did you find this useful? Give us your feedback
Citations
177 citations
42 citations
Cites background or methods or result from "2019 Cost of Wind Energy Review"
...…including a decline in the value of the U.S. dollar relative to the Euro; increased materials, energy, and labor input prices; a general increase in turbine manufacturer profitability due in part to strong demand growth; and increased costs for turbine warranty provisions (Moné et al. 2017)....
[...]
...dollar relative to the Euro; increased materials, energy, and labor input prices; a general increase in turbine manufacturer profitability due in part to strong demand growth; and increased costs for turbine warranty provisions (Moné et al. 2017)....
[...]
...Absent better data, and consistent with NREL assumptions, we assume that all plants have common total operating costs, at $51/kW-yr (Moné et al. 2017)....
[...]
...Since 2008, wind turbine prices have declined substantially, reflecting a reversal of some of the previously mentioned underlying trends that had earlier pushed prices higher (Moné et al. 2017) as well as increased competition among manufacturers and significant cost-cutting measures on the part of turbine and component suppliers....
[...]
...…have declined substantially, reflecting a reversal of some of the previously mentioned underlying trends that had earlier pushed prices higher (Moné et al. 2017) as well as increased competition among manufacturers and significant cost-cutting measures on the part of turbine and component…...
[...]
38 citations
Cites background or methods from "2019 Cost of Wind Energy Review"
...The wind turbine represents around 30% of the overall CapEx costs for a typical fixed-bottom offshore wind project [36]; however, these costs are negotiated on an individual project basis and are typically kept confidential by the supplier and developer [10]....
[...]
...Values for the capacity-weighted global average project installed in 2019 are also reported [36]....
[...]
...The cost reductions are defined relative to a baseline project repesentative of the capacity-weighted average project installed in 2019, he most recent year for which data are available [36]....
[...]
...The modeling tools required for this analysis also require several additional parameters to be defined that are not specified in [36], including a 34-year wind and wave time series with hourly resolution taken at a representative point in the North Atlantic (41◦N, 71◦W) pulled from the ERA5 reanalysis data set at a 100-m measurement height [38]....
[...]
...7 ercentage of the BOS costs [36], the reduction contributes significantly to the overall cost decrease....
[...]
30 citations
References
107 citations
"2019 Cost of Wind Energy Review" refers background or methods in this paper
...• LCOE estimates continue to show a downward trend from the “2010 Cost of Wind Energy Review” (Tegen et al. 2012) to 2019....
[...]
...The analysis and findings in this report helped generate the following conclusions: • LCOE estimates continue to show a downward trend from the “2010 Cost of Wind Energy Review” (Tegen et al. 2012) to 2019....
[...]
...For specific approaches regarding additional turbine parameters (e.g., power curves), see the “2010 Cost of Wind Energy Review” (Tegen et al. 2012)....
[...]
...…assumptions and ranges for key LCOE input parameters From the analysis detailed in this report, we derived the following key conclusions: • Land-based wind power plant LCOE estimates continue to show a downward trend from the “2010 Cost of Wind Energy Review” (Tegen et al. 2012) to the 2019 review....
[...]
...3 Approach This “2019 Cost of Wind Energy Review” applies a similar approach as the past cost of wind energy review reports (Tegen et al. 2012, 2013; Moné et al. 2015a, 2015b, 2017; Stehly et al. 2017, 2018, 2019)....
[...]
100 citations
"2019 Cost of Wind Energy Review" refers background in this paper
...…Operation and Maintenance Expenditures OpEx can vary greatly between projects for a number of reasons; however, the two largest cost drivers are the distance from the project to the maintenance facilities and the meteorological ocean climate at the site (Maples et al. 2013; Pietermen et al. 2011)....
[...]
...4 Offshore Operation and Maintenance Expenditures OpEx can vary greatly between projects for a number of reasons; however, the two largest cost drivers are the distance from the project to the maintenance facilities and the meteorological ocean climate at the site (Maples et al. 2013; Pietermen et al. 2011)....
[...]
73 citations
"2019 Cost of Wind Energy Review" refers background in this paper
...…(2020) announced a 2024 target for the commercial release of a 14-MW turbine model, with a power boost feature increasing the capacity to 15 MW. Incorporating larger turbines in a project’s design may contribute to LCOE reductions via reduced balance-of-plant and O&M costs (Musial et al. 2017)....
[...]
...Additional information on the types of fixed-bottom and floating wind substructures can be found in Musial et al. (2017)....
[...]
...More information on the global trends for offshore wind power plant performance can be found in Musial et al. (2017)....
[...]
...Incorporating larger turbines in a project’s design may contribute to LCOE reductions via reduced balance-of-plant and O&M costs (Musial et al. 2017)....
[...]
67 citations
"2019 Cost of Wind Energy Review" refers methods or result in this paper
...3 Approach This “2019 Cost of Wind Energy Review” applies a similar approach as the past cost of wind energy review reports (Tegen et al. 2012, 2013; Moné et al. 2015a, 2015b, 2017; Stehly et al. 2017, 2018, 2019)....
[...]
...Nevertheless, their exclusion is consistent with past economic analyses conducted by NREL (Stehly et al. 2018), as LCOE is not traditionally defined as a measure of all societal costs and benefits associated with power generation resources....
[...]