Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries
Reads0
Chats0
TLDR
In this paper, the authors employed a questionnaire survey to elicit the causes of this situation by interviewing 87 Vietnamese construction experts and found that there are no differences in the viewpoints between three principal parties in the project.Abstract:
In-planned duration and cost at project closing are the two of criteria of successful project and successful project management. In Vietnam, regularly, construction projects have met delays and cost overruns. This research has employed a questionnaire survey to elicit the causes of this situation by interviewing 87 Vietnamese construction experts. Twenty one causes of delay and cost overruns appropriate with building and industrial construction project were inferred and ranked with respect to frequency, severity and importance indices. Spearman’s rank correlation tests showed that there are no differences in the viewpoints between three principal parties in the project. A comparison of causes of time and cost overruns was done with various selected construction industries in Asia and Africa. Factor analysis technique was applied to categorize the causes, which yielded 7 factors: Slowness and Lack of constraint; Incompetence; Design; Market and Estimate; Financial capability; Government; and Worker. These findings might encourage practitioners to focus on delay and cost overruns problem that might have existed in their present or future projects.read more
Citations
More filters
Journal ArticleDOI
Exploring delay causes of road construction projects in Egypt
TL;DR: In this paper, a list of construction delay causes gathered from literature having different types of construction, different countries, different periods and different numbers of delay causes and delay groups is presented.
Journal ArticleDOI
Project management and its effects on project success: Cross-country and cross-industry comparisons
TL;DR: In this paper, the authors investigate the effects of project management on project success under the parameters of scheduling, cost, and margins, and show a significant and positive relationship between the response variable schedule with PM enablers and project management efforts in training and capabilities development.
Journal ArticleDOI
A fuzzy synthetic evaluation approach for risk assessment: a case of Singapore's green projects
TL;DR: In this paper, a risk assessment model was developed using the fuzzy synthetic evaluation approach to assess the risks in green building projects in Singapore, and the likelihood of occurrence, magnitude of impact and risk criticality of each risk factor, group and the overall risk were calculated.
Investigation into the Causes of Delays and Cost Overruns in Uganda's Public Sector Construction Projects
TL;DR: In this paper, the authors investigated the causes of construction project delays and cost overruns in Uganda's public sector and made recommendations for improved project management, a change from the traditional contract type to the design-build type and improved cash flow on the part of the client to reduce payment delays.
Journal ArticleDOI
Significant Factors Causing Cost Overruns in Large Construction Projects in Malaysia
TL;DR: In this article, the authors conducted a study to identify the significant factors causing cost overrun in large construction projects in Malaysia and found that the top three most significant factors of cost overrun are fluctuation of prices of material, cash flow and financial difficulties faced by contractors and poor site management and supervision.
References
More filters
Book
Research Methods for Business: A Skill Building Approach
Uma Sekaran,Roger Bougie +1 more
TL;DR: Examples are drawn from different areas of business - such as human resources management, strategic management, operations management, finance, accounting, and information management - to provide students with a comprehensive overview of the applications of research methods.
Book
Research Methods for Business
TL;DR: Hair, J.F., Money, A.H., Samouel, P.H. and Page, M. John Adams as discussed by the authors, "Research Methods for Business", Education + Training, Vol. 49 No. 4, pp. 336-337.
Journal ArticleDOI
Causes of delay in large construction projects
Sadi Assaf,Sadiq Al-Hejji +1 more
TL;DR: In this article, a survey on time performance of different types of construction projects in Saudi Arabia was conducted to determine the causes of delay and their importance according to each of the project participants, i.e., the owner, consultant and the contractor.
Journal ArticleDOI
Causes and effects of delays in Malaysian construction industry
Murali Sambasivan,Yau Wen Soon +1 more
TL;DR: In this article, the authors identified 10 most important causes of delay from a list of 28 different causes and 6 different effects of delay, and established an empirical relationship between each cause and effect.
Journal ArticleDOI
Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study
TL;DR: In this article, the authors present the results of a questionnaire survey conducted to identify and evaluate the relative importance of the significant factors contributing to delay and cost overruns in Ghana groundwater construction projects.
Related Papers (5)
Causes and effects of delays in Malaysian construction industry
Murali Sambasivan,Yau Wen Soon +1 more