IEA Wind Task 26: The Past and Future Cost of Wind Energy, Work Package 2
Summary (4 min read)
1 Introduction
- This report has been developed as part of the International Energy Agency (IEA) Wind Implementing Agreement Task 26, The Cost of Wind Energy, and builds on the prior work of this task to estimate the 2008 cost of wind energy among the participating countries (Schwabe et al. 2011) .
- Additional input to this report comes from published data as well as data provided to the Task 26 Working Group by participating members.
- To be clear, this report does not make new, long-term cost-of-energy forecasts.
2 Trends in Wind Energy Capital Costs and Performance
- Here the authors examine capital cost and performance trends from the 1980s through present day.
- These time periods cover both significant cost reductions as well as the period of cost increases observed during the last decade.
- Included is a discussion of the drivers of both capital cost reductions and increases.
- Developments in turbine performance since the 1980s are also discussed; however, performance data are focused primarily on the more recent period, from the turn of the century to today's current turbine offerings.
2.1 Capital Cost Reductions: 1980-2003
- From the 1980s to the early 2000s, average capital costs for wind energy projects declined markedly.
- Wiser and Bolinger 2011 , Nielsen et al, also known as Sources.
- Larger turbines provided access to better wind resources while lowering the plant-wide parts count and generating turbine-level economies of scale for many components for which costs do not vary proportionally with turbine size (e.g., controls).
2.2 Capital Cost Increases: 2004-2009
- Further discussion and analysis of the role of some of these factors in driving historical onshore wind energy costs is included in Milborrow (2008) , Blanco (2009) , and Dinica (2011) .
- Moreover, other authors note the importance of many of these same factors in driving up the cost of offshore wind energy (e.g., Carbon Trust 2008 , Greenacre et al. 2010) , as well as other forms of electricity generation equipment (e.g., Chupka and Basheda 2007, Winters 2008 ) over a similar time frame.
2.3 Performance Increases: 1980-2010
- As a result of the limitations noted above, fleet-wide capacity factor data are incapable of demonstrating the true level of performance improvement achieved over the past three decades.
- By evaluating overall multi-year average capacity factor changes within specific wind power classes and for specific project vintages, greater insights into the overall magnitude of technical improvement can be gained.
- Such an exercise is particularly important in places like Spain (and many other parts of the world) where projects have increasingly been installed in lower wind power class sites, and the actual degree of capacity factor improvement over time within individual wind resource classes is less apparent (Wiser 2011 , Dinica 2011) .
- 8 Figure 6 illustrates the substantial improvements over time in multi-year average capacity factors that have been observed from projects installed in the United States when sorted by wind power class and project vintage.
- These improvements have been directly linked to the development of taller towers and larger rotors (Wiser 2010 ).
2.4 Recent and Near-term Trends in Capital Cost and Performance
- Hub heights and rotor diameters have continued to trend toward larger machines, suggesting that turbine performance improvements will also continue.
- Preliminary analysis conducted by Wiser et al. (2012) suggests that capacity factors for projects to be installed with current state-of-the-art technology in the United States will improve significantly within a given wind power class, relative to older technology .
- Moreover, also shown in the figure, the most significant performance improvements are occurring in equipment designed for low wind speed sites (typical average hub-height wind speeds of 7.5 m/s).
- As a result of these technical and design advancements, Wiser et al. (2012) find that the amount of U.S. land area that could achieve 35% or higher wind project capacity factors has increased by as much as 270% when going from turbines commonly installed in the 2002-2003 time frame to current low wind speed turbine offerings.
3 Impact of Capital Cost and Performance Trends on Levelized Cost of Energy
- As noted earlier, attempting to elicit LCOE trends from either capital cost or performance independently is tenuous.
- Data shown here generally reflect the impact on LCOE from capital cost and performance changes.
- More precise estimates would also factor in the effects of changes in O&M costs, major equipment replacement costs, financing costs, and actual turbine lifetime.
- Due to limited data availability, the latter variables were not considered in the analysis presented in Section 3.2.
- Also note that the LCOE figures presented in this section exclude available incentives that might affect the price of wind energy in wholesale markets.
3.1 Historical LCOE Trends: 1980-2009
- Significant reductions in capital cost and increases in performance between 1980 and 2003 had the combined effect of dramatically reducing the LCOE of wind energy.
- During this time, capital cost and performance trends were both generally aligned with substantial capital cost declines and performance improvements.
- As a result, there was little risk associated with an exclusive focus on one or the other when attempting to understand broad trends in the LCOE of wind.
4.2 Expert Elicitation
- This approach is based on surveying or interviewing industry executives and technology design experts.
- Interviews are typically focused at the turbine component and system level and may also attempt to capture trends in various aspects of installation costs (e.g., underground cabling, erection costs, and required on-site monitoring infrastructure).
- By evaluating the potential for cost reductions or performance improvements at the component or system level and combining the estimated potential from an array of concrete possible technological advancements, this approach constitutes a simple but technology-rich, bottom-up analysis.
- It also introduces a relatively high level of subjectivity into the analysis, as the responses to the elicitation may be affected by the design of the data collection instrument and by the individuals selected to submit their views through that instrument.
4.3 Engineering Model
- In addition to primarily being focused on the near to medium term, the main limitation of the engineering model approach is that it requires highly sophisticated design and cost models to capture the full array of component-and system-level interactions.
- Often the level of sophistication achieved with today's modeling tools is insufficient to truly capture the systemlevel interactions that are common in wind turbine design.
- 18 Accordingly, the projected costs are generally based on the impact of a particular technical innovation, all else being constant.
4.3.1 Engineering Model Examples
- One of the prime examples of the engineering modeling approach comes from the U.S. Department of Energy's WindPACT project (e.g., Bywaters et al. 2005, Malcolm and Hansen 2002) .
- These results were ultimately tied to cost functions to quantify their impact on turbine and project costs (Fingersh et al. 2006 ).
- More recent NREL modeling work that builds upon these studies suggests that performance increases on the order of 20% and cost reductions on the order of 10% over the next one to two decades are possible but may require additional technological advancements not captured by the WindPACT studies (e.g., Lantz and Hand 2011) .
4.4 Sources of Cost Reduction Identified by Expert Elicitation and Engineering
- Table 1 summarizes the broad categories of opportunities envisioned to apply to onshore wind energy projects, based on engineering studies and expert elicitation.
- Much of the opportunity to drive down costs is perceived to be in the design and performance of wind turbines because of their critical role in calculating wind energy's LCOE; initial turbine expenditures alone account for roughly 70%-75% of project capital costs (Wiser and Bolinger 2011, Blanco 2009 ) and about 60% of lifetime project costs (Blanco 2009 ).
5 Conclusions
- Robust data collection is needed across the array of variables that must be factored into estimating LCOE (e.g., capital cost, capacity factor, O&M costs, component replacement rates and costs, and financing costs) and in each of the wind energy markets around the globe.
- Such data would allow historical LCOE trends to be more closely analyzed, with insights gleaned both through more-sophisticated learning curve analysis as well as bottom-up assessments of historical cost drivers.
- An enhanced capacity to model the cost and performance impacts of new technological innovation opportunities, taking into account the full system dynamics that result from a given technological advancement, is also essential.
Did you find this useful? Give us your feedback
Citations
630 citations
430 citations
304 citations
109 citations
87 citations
References
1,028 citations
"IEA Wind Task 26: The Past and Futu..." refers background in this paper
...Much of the opportunity to drive down costs is perceived to be in the design and performance of wind turbines because of their critical role in calculating wind energy’s LCOE; initial turbine expenditures alone account for roughly 70%–75% of project capital costs (Wiser and Bolinger 2011, Blanco 2009) and about 60% of lifetime project costs (Blanco 2009)....
[...]
...Further discussion and analysis of the role of some of these factors in driving historical onshore wind energy costs is included in Milborrow (2008), Blanco (2009), and Dinica (2011)....
[...]
...…be in the design and performance of wind turbines because of their critical role in calculating wind energy’s LCOE; initial turbine expenditures alone account for roughly 70%–75% of project capital costs (Wiser and Bolinger 2011, Blanco 2009) and about 60% of lifetime project costs (Blanco 2009)....
[...]
...Further discussion and analysis of the role of some of these factors in driving historical onshore wind energy costs is included in Milborrow (2008), Blanco (2009), and Dinica (2011). Moreover, other authors note the importance of many of these same factors in driving up the cost of offshore wind energy (e....
[...]
551 citations
"IEA Wind Task 26: The Past and Futu..." refers background in this paper
...As the wind industry has only recently become truly global, many past studies focused on deployment within a given country or regional market (e.g., Neij 1997, Mackay and Probert 1998, Wene 2000, and Söderholm and Sundqvist 2007)....
[...]
520 citations
"IEA Wind Task 26: The Past and Futu..." refers background or methods in this paper
...These results were ultimately tied to cost functions to quantify their impact on turbine and project costs (Fingersh et al. 2006)....
[...]
...…Baseline Design 0 5000 10000 15000 20000 25000 30000 0 10 20 30 40 50 60 70 M as s (k g) Rotor Radius (m) Commercial Blade Data Source: Based on Fingersh et al., 2006 Innovation for Our Energy Future Wind Turbine Blade Innovation Pathway WindPACT Baseline Design LM Glasfiber…...
[...]
...…10 20 30 40 50 60 70 M as s (k g) Rotor Radius (m) LM Glasfiber Blades Commercial Blade Data TPI Innovative Blade Concepts Source: Based on Fingersh et al., 2006 Innovation for Our Energy Future NREL Engineering Model Analysis Scope 12 Objective • Quantify the value of potential…...
[...]
...Advanced design concepts considered by Fingersh et al. (2006) suggest that higher tower heights might be achieved in the future with only incremental cost increases....
[...]
...…Blades 0 5000 10000 15000 20000 25000 30000 0 10 20 30 40 50 60 70 M as s (k g) Rotor Radius (m) LM Glasfiber Blades Commercial Blade Data Source: Based on Fingersh et al., 2006 75 Innovation for Our Energy Future Wind Turbine Blade Innovation Pathway WindPACT Baseline Design WindPACT Final…...
[...]
373 citations
"IEA Wind Task 26: The Past and Futu..." refers background or methods in this paper
...Neij (2008), in work conducted for the European Union’s New Energy Externalities Developments for Sustainability (NEEDS) project, combined expert elicitation with learning curve analysis to estimate that future turbine costs 21 could be approximated with a learning rate of about 10% and that…...
[...]
...Looking forward, offshore wind costs are generally expected to follow a steeper downward trajectory than costs for onshore wind energy (Neij 2008, Wiser et al. 2011, Doyle et al. 2011, and ARUP 2011)....
[...]
313 citations