Real option applications in megaproject planning: trends, relevance and research gaps. A literature review
read more
Citations
The Oxford handbook of megaproject management
Application of real options in carbon capture and storage literature: Valuation techniques and research hotspots
Explaining Uncertainty Avoidance in Megaprojects: Resource Constraints, Strategic Behaviour, or Institutions?
A real options framework for adaptive urban design
Using Real Options Thinking to Value Investment Flexibility in Carbon Capture and Utilization Projects: A Review
References
The Pricing of Options and Corporate Liabilities
Determinants of corporate borrowing
Investment Under Uncertainty
Kostenunterschätzung bei öffentlichen bauprojekten: fehler oder lüge? (Underestimating Costs in Public Works Projects: Error or Lie?)
Underestimating Costs in Public Works Projects: Error or Lie?
Related Papers (5)
Research Infrastructure Megaproject (RIMPS) management in an ecosystem perspective Literature Review
Frequently Asked Questions (13)
Q2. What are the future works mentioned in the paper "Real option applications in megaproject planning: trends, relevance and research gaps. a literature review" ?
For this, the authors believe the main starting point for further research should be to interact more with planning practitioners and decision-makers in megaprojects, and that the process of interaction should be documented in publications. Question four aims to encourage more awareness of the complex planning conditions and context in which real options are applied, acknowledging the diverse possibilities of applications regarding, for example, different megaproject types, phases and procurement methods. To sum up, future research should focus on how ROT can actually improve and contribute to decision-making in megaprojects. The authors believe this review paper has raised the following research questions that should be added to the research agenda of those interested in uncertainty, risk and flexibility, or applying real options in megaprojects: 1. How do they identify uncertainties collaboratively and reach a consensus on which uncertainties are important and how they should be further assessed, modelled, and managed, given the context of multiple uncertainties in megaprojects ?
Q3. What is the main approach to megaproject management?
Megaproject management is based on the dominant ‘predict and control’ approach (Koppenjan et al., 2011), attempting to reduce complexity.
Q4. What is the advantage of ROT for megaprojects?
Uncertainty and flexibility then become less vague terms once they are given a quantifiable face, increasing the relevance and added value of ROT for megaprojects.
Q5. What is the role of qualitative case studies in the assessment of options in megaprojects?
Valuing flexibility remains an important point of relevance, but in-between ‘baby-steps’, including qualitative case studies, are required to increase their knowledge on real options integration in megaproject practice.
Q6. What is the role of participatory research in planning practice?
For current planning practices, such participatory research will allow for the explicit acknowledgement of the importance of uncertainty identification, communication and assessment.
Q7. What is the purpose of question four?
Question four aims to encourage more awareness of the complex planning conditions and context in which real options are applied, acknowledging the diverse possibilities of applications regarding, for example, different megaproject types, phases and procurement methods.
Q8. What is the main idea of adaptive planning in megaprojects?
ROT thinking and modelling in megaprojects could help facilitate a shift from the dominant but unrealistic premise that the authors can exactly predict and forecast the future, to the more realistic premise that the authors should accept an uncertain future.
Q9. What is the role of risk mitigation measures in megaprojects?
Risk mitigation measures are an important part of megaprojects, especially when balancing risks between public and private actors in PPPs.
Q10. What are the three commonly used real options?
The three most applied ‘classic’ real options are the options to delay (12), scale (8) – expand or contract – and abandon (6) (Table 5).
Q11. Why does the paper focus on megaprojects?
the paper focuses on megaprojects only because of the strongly developed theories in planning literature regarding this subject.
Q12. What is the time to broaden their research scope?
The time has come to broaden their research scope and figure out how to translate theory into practice through interaction with the field of planning and megaprojects.
Q13. What is the role of research in the development of a toolkit for dealing with uncertainty?
Research in interaction with planning experts and practitioners could help to offer insights on how to develop a toolkit to aid and improve dealing with uncertainties through flexibility in the planning, design and decision-making of megaprojects.