Optimal Transmission Switching
read more
Citations
Mixed-integer nonlinear optimization
Tight Mixed Integer Linear Programming Formulations for the Unit Commitment Problem
Optimal Transmission Switching With Contingency Analysis
Co-Optimization of Generation Unit Commitment and Transmission Switching With N-1 Reliability
Optimal transmission switching with contingency analysis
References
Integer and Combinatorial Optimization
A New Benders Decomposition Approach to Solve Power Transmission Network Design Problems
A market mechanism for electric power transmission
Solving Real-World Linear Programs: A Decade and More of Progress
Related Papers (5)
Frequently Asked Questions (15)
Q2. What have the authors stated for future works in "Optimal transmission switching" ?
More research, particularly in the areas of reliability and cost or surplus allocation, will provide more insight into the possibilities for controllable, more flexible networks to be part of the solution for meeting growing demand in a transmission-constrained world.
Q3. Why is it possible to reduce the dispatch cost?
Because of the peculiar characteristics of electricity, it is possible to improve the dispatch cost by removing a line from the network.
Q4. What is the common explanation for the cost of opening a line?
It has been shown that Wheatstone bridges can be associated with Braess Paradox, in which adding a line to a network can increase the cost of using that network [16] [24].
Q5. What is the effect of the Kirchhoff law on the power flow of an open line?
Whereas this formulation would allow no flow on an open line, it also limits power flow to zero on all lines that share terminal nodes with the open line, because the voltage angle difference is forced to zero.
Q6. What is the simplest way to make the objective function more robust?
Making the objective function more robust would ensure all appropriate operating costs were being considered in the solution.∑= g ngng PcMaxTC s.t.: (1) maxmin nnn θθθ ≤≤(2) for all g and n maxmin ng PngPng P ≤≤(3) maxmin nk PnkPnk P ≤≤ for all k and n(4) for all n 0=∑−∑−∑− dgk ndPngPnkP (5) ( ) 0=−− nkPmnkB θθ for all lines k with endpoints n and mThe constraints represent physical operating limits of thenetwork.
Q7. What is the way to simulate different loading scenarios?
To simulate different loading scenarios, the authors created two additional cases, called Peak and Off Peak, in which each load in the case above is scaled either up or down by ten percent, respectively.
Q8. Why is the power flow of an open line more complicated than limiting it to Pnk?
Because of the constraint representing Kirchhoff’s laws, the formulation of the problem is more complicated than simply limiting the power flow to Pnkmax or Pnkmin times the binary variable.
Q9. How many violations did the authors find in the base case?
This resulted in 28 violations: 23 violations that occurred for the same contingency and on the same line as for the base case, and five violations not occurring in the base case.
Q10. What is the power flow from line k to node n?
Pnk represents the power flow from line k to node n, and therefore can be positive or negative depending on whether power is flowing into or out of the node.
Q11. What is the purpose of this paper?
This paper presents an optimization model for determining optimal transmission network topology and generation output to meet a static load.
Q12. What is the general trend in the optimally-open lines?
There is no general trend in physical characteristics of the optimally-open lines; rather the decision to open a line or keep it closed depends on specific operating conditions, loads and generator costs.
Q13. How many lines are loaded to capacity in the Peak case?
In the j=1 (feasible) case, three of these lines are loaded to capacity, and the others are within 1, 7 and 20 percent of being fully loaded.
Q14. Why was PowerWorld used for this analysis?
rather than the GAMS model discussed above, was used for this analysis because it includes a well-tested contingency analysis tool, and using this existing tool was adequate and more convenient than developing one in GAMS.
Q15. How much system cost was decreased for the Peak case?
For each of these two new cases, the MIP was performed with the GUB constraint, for j = 0,…,5 and j = 0,…,4. System cost decreased by 12.2 percent for the Peak load case for j = 5, and by 17.8 percent for the Off-Peak case for j = 4.