Project Robust Scheduling Based on the Scattered Buffer Technology

Nansheng Pang, +2 more
- 02 Apr 2018 - 
- Vol. 8, Iss: 4, pp 541
TLDR
Through the comprehensive analysis of various factors that influence the solution activity, this paper proposes a metric that is used to evaluate the solution robustness of the project scheduling, and this metric is taken as the optimization goal.
Abstract
The research object in this paper is the sub network formed by the predecessor’s affect on the solution activity. This paper is to study three types of influencing factors from the predecessors that lead to the delay of starting time of the solution activity on the longest path, and to analyze the influence degree on the delay of the solution activity’s starting time from different types of factors. On this basis, through the comprehensive analysis of various factors that influence the solution activity, this paper proposes a metric that is used to evaluate the solution robustness of the project scheduling, and this metric is taken as the optimization goal. This paper also adopts the iterative process to design a scattered buffer heuristics algorithm based on the robust scheduling of the time buffer. At the same time, the resource flow network is introduced in this algorithm, using the tabu search algorithm to solve baseline scheduling. For the generation of resource flow network in the baseline scheduling, this algorithm designs a resource allocation algorithm with the maximum use of the precedence relations. Finally, the algorithm proposed in this paper and some other algorithms in previous literature are taken into the simulation experiment; under the comparative analysis, the experimental results show that the algorithm proposed in this paper is reasonable and feasible.

read more

Citations
More filters
Journal ArticleDOI

A Proactive Robust Scheduling Method for Aircraft Carrier Flight Deck Operations with Stochastic Durations

TL;DR: Simulation results shows that the HTLBO algorithm outperforms both some other state-of-the-art algorithms for deterministic cases and some existing algorithms for stochastic project scheduling, and the robustness of the flight deck operations can be improved with the proposed resource allocation schemes and CPC policy.
Journal ArticleDOI

The integration of resource allocation and time buffering for bi-objective robust project scheduling

TL;DR: This paper aims at constructing a proactive schedule that is not only short in time but also less vulnerable to disruptions, and demonstrates the superiority of the combination between resource allocation and time buffering as well as the effectiveness of the proposed two-stage algorithm for generating proactive project schedules with composite robustness.
Journal ArticleDOI

A Construction Schedule Robustness Measure Based on Improved Prospect Theory and the Copula-CRITIC Method

TL;DR: A construction schedule robustness measure based on improved prospect theory and the Copula-criteria importance through intercriteria correlation (CRITIC) method is proposed, and an information-entropy-based evidence reasoning method is applied to combine subjective and objective weights together while identifying their validity.
Journal ArticleDOI

A Robust Scheduling Optimization Method for Flight Deck Operations of Aircraft Carrier With Ternary Interval Durations

TL;DR: The results demonstrate that the proposed robust scheduling method can effectively improve the robustness of the flight deck operations.
Journal ArticleDOI

Financial Optimization of the Resource-Constrained Project Scheduling Problem with Milestones Payments

Marcin Klimek
- 12 Jan 2021 - 
TL;DR: This article presents the resource-constrained project scheduling problem with the discounted cash flow maximization criterion from the perspective of a contractor and proposes dedicated techniques to generate solutions and a simulated annealing algorithm to solve the problem.
References
More filters
Journal ArticleDOI

Insertion techniques for static and dynamic resource-constrained project scheduling

TL;DR: A flow network model, based on a new polynomial insertion algorithm taking advantage on the flow structure, is proposed for static and dynamic scheduling methods for static resource-constrained project scheduling problem.
Journal ArticleDOI

The use of buffers in project management: The trade-off between stability and makespan

TL;DR: An extensive analysis of the results of a simulation experiment is provided to investigateWhether it is beneficial to concentrate safety time in project and feeding buffers, or whether it is preferable to insert time buffers that are scattered throughout the baseline project schedule in order to maximize schedule stability.
Journal ArticleDOI

Proactive heuristic procedures for robust project scheduling: An experimental analysis

TL;DR: This paper introduces multiple algorithms to include time buffers in a given schedule while a predefined project due date remains respected and multiple efficient heuristic and meta-heuristic procedures are proposed to allocate buffers throughout the schedule.
Journal ArticleDOI

A purely proactive scheduling procedure for the resource-constrained project scheduling problem with stochastic activity durations

TL;DR: A new procedure for generating a proactive baseline schedule for the resource-constrained project scheduling problem is developed that is completely independent of the reactive policy applied, and outperforms two other published methods, assuming different robustness measures.
Journal ArticleDOI

An adjustable robust optimization model for the resource-constrained project scheduling problem with uncertain activity durations

TL;DR: A general decomposition approach is proposed to solve the robust counterpart of the resource-constrained project scheduling problem, further tailored to address the uncertainty set with the protection factor.
Related Papers (5)